Rep. Jim Walsh issues statement on WSDOT’s staggering cost increases: a $3.5 to $4 billion surge to remove fish migration barriers
CONTACT: Hanna Scott, Public Information Officer | 360-968-3938
Rep. Jim Walsh issues statement on WSDOT’s staggering cost increases: a $3.5 to $4 billion surge to remove fish migration barriers
In a recent House Transportation Committee briefing, the Washington State Department of Transportation (WSDOT) revealed a substantial increase in costs for the removal of fish passage barriers beneath highways. WSDOT testified that the projected cost for the project has surged by $3.5 to $4 billion, for a total cost of up to $7.8 billion—a staggering increase from initial estimates.
The removal of these barriers, commonly referred to as culverts, was mandated by a court order to enhance fish passage statewide. The state’s obligation to undertake this initiative was affirmed in 2018 by a U.S. Supreme Court decision, upholding a lower court order that held the state responsible for the removal of culverts obstructing fish migration.
The additional costs reported by WSDOT pose a threat to an already strained transportation budget, potentially resulting in further delays to essential highway and road maintenance projects across the state. This is further compounded by a looming deadline set by a federal judge in response to a lawsuit filed by Washington tribes, leaving the Legislature with limited options but to act promptly.
Rep. Jim Walsh, R-Aberdeen, expressed his astonishment at the jaw-dropping rise in costs in the following statement:
“Several years ago, when we initially worked on funding the culvert replacement project to facilitate fish passage upstream, the lawsuit’s terms and negotiated settlement included a package of culverts. At that time, WSDOT’s estimated cost for Washington state taxpayers was around $1.7 billion.
“In response, Republicans in the Legislature, collaborating with our Democrat colleagues, created a funding plan for the project that would have completed it by now. Unfortunately, the Legislature did not act promptly; instead, the majority party delayed it for several more years. By the time a plan was approved, the price had escalated to nearly $3.5 billion, doubling the original estimate.
“Now, as the current version of the project has finally started, WSDOT informs the Legislature that the cost has increased by an additional $3.5 to $4 billion, resulting in a total project cost four times the original estimate!
“This culvert project has grown out of control. It serves as yet another regrettable example of bumbling bureaucratic mismanagement. Why does this happen? Poor oversight, insufficient project supervision, enabled by decades of one-party control in Washington state government. Of course, the cost of this failure is paid by Washington’s working people and families—in higher gas and diesel prices, higher grocery prices, and higher rents and mortgage payments. We owe it to everyone in Washington to manage state projects with more competence and less failure.”